Clayton Expansion Project – Week 15 Update

As the cool weather slowly makes its way here, our team is continuing to push through and are staying on top of things to get this project completed.

Last week, we finished pulling on Tatlock Road, and we started on Wolf Grove Road, where we were able to pull 1 km.

We made great progress last week, with our totals on the project now: 14.6 km trenched, 10.3 km pulled, and 9.3 km spliced.

Are you wondering if you will be able to have a fibre network connection at your home? For more information, please contact:

We’re Hiring!

Are you or someone you know, looking for a job? We are always looking for field technicians! We are also currently looking for help with remediation in Clayton. If you or someone you know is interested, send your resume and cover letter to hr@corp.storm.ca

As always, don’t forget to follow us on social media: Facebook, Instagram, Twitter, LinkedIn

Waterfront view of Clayton, Ontario. There are trees and houses in the background. The water is calm enough to see the reflection of trees, houses, and the sky in the water.

MORE POSTS

2015 Canada Army Run

2015 Canada Army Run

2015 Canada Army RunOn the morning of Sunday, September 20, 2015, the 2015 Canada Army Run took...

CONTACT US
Head Office

1760 Courtwood Crescent
Ottawa, ON K2C 2B5

TOLL-FREE: 1-866-257-8676

Rediscover Customer Service.

 

HOURS OF OPERATIONS

Support Hours:
Monday-Friday 8am-9pm
Saturday-Sunday 9am-5pm

Sales Hours:
Monday-Friday 8am-4pm

Billing Hours:
Monday-Friday 9am-5pm

TERMS OF SERVICE   |   PRIVACY POLICY  |  CORPORATE RESPONSIBILITY POLICYACCESSIBILITY  VOIP 911 TERMS

© Copyright 1996-2022 Storm Internet Services |  All Rights Reserved.