Clayton Expansion Project – Week 22 Update

Clayton Expansion Project – Week 22 Update

The race is on to get as much completed before the snow starts to come as we can! This week the team was in Lanark Highlands and was able to complete trenching on 12C.  All private roads in Clayton are completed and live! If you have any images of the team working on the project, send them to shetherington@corp.storm.ca to be featured on our social media! We’re Hiring! We are currently hiring...

read more
Clayton Expansion Project – Week 21 Update

Clayton Expansion Project – Week 21 Update

Last week, the team was able to complete pulling fibre on Wolf Grove Road. They also competed pulling the last of the private roads! This week, the team will be focusing on trenching on 12C and splicing everything that was pulled last week. As a reminder, our machinery was vandalized about 3 weeks ago, and our pylons were stolen in late summer/early fall. When our equipment is vandalized or...

read more
UCI 1-Hour World Record Attempt

UCI 1-Hour World Record Attempt

Angella Goran - founder of SokJok, first female founder of a Neobank in Canada, and long-time friend of our CEO, Birket. Storm Internet is proud to announce that we are sponsoring Angella in her journey to a world record for indoor cycling, competing in the UCI 1 Hour World Record attempt in Mexico on May 4th, 2022. Over the next six months, we’ll be following her journey on the road to the...

read more
Clayton Expansion Project – Week 20 Update

Clayton Expansion Project – Week 20 Update

We are nearly done with all the private roads in Clayton! It has been a long process, but we’re glad to start connecting new customers! This week, we are going to be completing some more fibre pulling. Once that’s finished, the team will be installing backbone fibre on the last of the private roads. Once that’s completed, Storm Internet will be moving to Lanark Highlands. As one last reminder,...

read more
Clayton Expansion Project – Week 19 Update

Clayton Expansion Project – Week 19 Update

We’re into November, and the teams are continuing to work every day to get new customers connected to the fibre network. Thankfully the weather has been great for this time of year, so we have not been experiencing weather delays. Last week, the Storm team was able to trench a total of 2km. The team was unable to pull or splice. This week we will be completing the area we were on last week...

read more
Clayton Expansion Project – Week 18 Update

Clayton Expansion Project – Week 18 Update

The team was ready to go last week to continue on the project. Even though we did manage to pull some fibre, we did run into a few delays during the week. Due to the rainy weather, we were unable to work. However, the real setback was when we had our equipment vandalized. Unfortunately, when our equipment is vandalized or stolen, it can delay the team by a few days, depending on how serious the...

read more
Clayton Expansion Project – Week 17 Update

Clayton Expansion Project – Week 17 Update

Due to some inclement weather last week, we unfortunately ran into a few unexpected issues, and we were unable to continue to pull fibre on Wolf Grove Road, or begin trenching on Lakeland Lane. This week, the team will be working on pulling on Wolf Grove Road, and trenching on Lakeland Lane. We will be working efficiently and effectively to make up for any lost time. We’re Hiring! Are you or...

read more
Clayton Expansion Project – Week 16 Update

Clayton Expansion Project – Week 16 Update

Our fibre expansion project is coming along nicely. With the weather starting to cool off, the teams are eager to get our customers up and running! Our team started pulling fibre on Wolf Grove Road last week, and will continue this step this week. This week, we are also scheduled to start trenching on Lakeland Lane. Are you wondering if you will be able to have a fibre network connection at your...

read more
Clayton Expansion Project – Week 15 Update

Clayton Expansion Project – Week 15 Update

As the cool weather slowly makes its way here, our team is continuing to push through and are staying on top of things to get this project completed. Last week, we finished pulling on Tatlock Road, and we started on Wolf Grove Road, where we were able to pull 1 km. We made great progress last week, with our totals on the project now: 14.6 km trenched, 10.3 km pulled, and 9.3 km spliced. Are you...

read more
Thanksgiving Holiday

Thanksgiving Holiday

In recognition of this year's Thanksgiving holiday, all of our offices will be closed on Monday, October 11th, 2021. Client Services will be open Saturday, October 9th, and Sunday October 10th. Representatives will be available from 9 AM - 5PM. Our regular business hours will resume on Tuesday, October 12th, at 8 AM. Emergency and on-call services will operate as normal. We wish everyone a Happy...

read more

CONTACT US
Head Office

1760 Courtwood Crescent
Ottawa, ON K2C 2B5

TOLL-FREE: 1-866-257-8676

Rediscover Customer Service.

 

HOURS OF OPERATIONS

Support Hours:
Monday-Friday 8am-9pm
Saturday-Sunday 9am-5pm

Sales Hours:
Monday-Friday 8am-4pm

Billing Hours:
Monday-Friday 9am-5pm

TERMS OF SERVICE   |   PRIVACY POLICY  |  CORPORATE RESPONSIBILITY POLICYACCESSIBILITY  VOIP 911 TERMS

© Copyright 2021 Storm Internet Services |  All Rights Reserved.