Clayton Expansion Project – Week 21 Update
Last week, the team was able to complete pulling fibre on Wolf Grove Road. They also competed pulling the last of the private roads!
This week, the team will be focusing on trenching on 12C and splicing everything that was pulled last week.
As a reminder, our machinery was vandalized about 3 weeks ago, and our pylons were stolen in late summer/early fall. When our equipment is vandalized or stolen, it unfortunately delays the process. Pylons are also in place for everyone’s safety, both staff and the public. If you know anything about the vandalizations that happened at the end of October, please contact Michel at 613-567-6585 ext. 250.
If you have any images of the team working on the project, send them to shetherington@corp.storm.ca to be featured on our social media!
We’re Hiring!
We are currently hiring for two field techs – one in Ottawa, and one in Chesterville. To learn more about the positions and to apply, visit our careers page!
MORE POSTS
Clayton Expansion Project – Week 13 Update
Clayton Expansion Project - Week 13 UpdateIt’s almost October, and we are already 13 weeks into...
Clayton Expansion Project – Week 12 Update
Clayton Expansion Project - Week 12 UpdateWe are getting closer to the end of the project, and we...
Storm Internet is in Barrie, Ontario!
Storm Internet is in Barrie, Ontario!Back in fall of 2019, we were given the opportunity to...
CONTACT US
Head Office
1760 Courtwood Crescent
Ottawa, ON K2C 2B5
TOLL-FREE: 1-866-257-8676
Rediscover Customer Service.
HOURS OF OPERATIONS
Support Hours:
Monday-Friday 8am-9pm
Saturday-Sunday 9am-5pm
Sales Hours:
Monday-Friday 8am-4pm
Billing Hours:
Monday-Friday 9am-5pm
BUSINESS SERVICES
RESIDENTIAL SERVICES
TERMS OF SERVICE | PRIVACY POLICY | CORPORATE RESPONSIBILITY POLICY | ACCESSIBILITY | VOIP 911 TERMS
© Copyright 1996-2022 Storm Internet Services | All Rights Reserved.