Clayton Expansion Project – Week 13 Update

Clayton Expansion Project – Week 13 Update

It’s almost October, and we are already 13 weeks into the project! It’s hard to believe we started this project back in July. We’re looking forward to connecting more customers to the fibre network in the upcoming weeks. This week, our team is continuing to work on Wolf Grove Road. The trenching crew will be out working on the last part of Wolf Grove, which is just under 1 km past 12th...

read more
Clayton Expansion Project – Week 12 Update

Clayton Expansion Project – Week 12 Update

We are getting closer to the end of the project, and we are continuing to work hard every day to keep the project moving along. Thankfully, Mother Nature has been on our side so far - and we’re hoping it stays that way this week! Last week was a busy week for the Storm team in Clayton. We were able to make great progress on splicing, completing Clayton Road, 3C and 4B. The team also began and...

read more
Storm Internet is in Barrie, Ontario!

Storm Internet is in Barrie, Ontario!

Back in fall of 2019, we were given the opportunity to provide wireless Internet to the waterfront of Barrie, Ontario, specifically between Heritage Park and 205 Lakeshore Drive. Those who are walking along the waterfront, or spending the day at the beach, are able to connect whenever they want to the Storm engineered and installed wireless Internet . This was made possible by provisioning 20...

read more
Clayton Expansion Project – Week 11 Update

Clayton Expansion Project – Week 11 Update

We’re already halfway through September, which means we are officially halfway through the project. We have gotten a lot of work done over the past couple of months,  and we look forward to having more customers connected every week. Last week, the trenching process continued on Tatlock Road, and will be finished this week. Also, the fibre has been pulled in the conduit on all of Clayton Road,...

read more
Clayton Expansion Project – Week 10 Update

Clayton Expansion Project – Week 10 Update

The summer has flown by and we are already one week into September, and we are progressing nicely on our fibre expansion project in Clayton, ON. We started back in July and are expected to go until mid-November, 2021. Since the start of the project, we have worked on many roads, including Ramsay Concession 3C, Bowland Road, and Clayton Road. But what have we been working on over the past week?...

read more
Now Accepting Visa Debit Cards

Now Accepting Visa Debit Cards

At Storm Internet, we are happy to announce that we are now able to accept Visa Debit cards! This has been something we have been looking into for a while, and it's finally here! Making payments online has never been easier. You can view your account details at portal.storm.ca For any questions or concerns, give us a call at 1.866.257.8676 CONTACT USHead Office 1760 Courtwood CrescentOttawa, ON...

read more
Clayton Expansion Project – Week 9 Update

Clayton Expansion Project – Week 9 Update

We’re at the end of August, and we’re already onto week 9 of our Fibre Expansion Project. Every week, we're working on something different. We are even starting to connect customers! This week, the trenching process begins on Tatlock Road between Galbraith and Short while our second team works on cleaning up on 3B and 4C. Later this week, we will be pulling fibre in the conduit on Clayton Road. ...

read more
Clayton Expansion Project – Week 8 Update

Clayton Expansion Project – Week 8 Update

It’s hard to believe that we’re already two months into this expansion project! Over the past two months, we’ve worked on multiple roads in the Clayton area, including Bowland, Clayton, and Tatlock Roads. We’re continuing to move forward and start trenching on new roads. Here is the latest updates: Last week on Clayton Road, our fibre pulling team pulled the fibre pull string through the...

read more
Clayton Expansion Project – What Have we Been up to?

Clayton Expansion Project – What Have we Been up to?

Over the past couple of weeks, the Storm team has been working their way through Clayton, Ontario, to provide residents with a Fibre to the Home connection. Here’s a recap of what’s been going on over the past three weeks: Our trenching team has been working on trenching Clayton road for the past two weeks. They’re nearing the final stages of trenching for this section of road, hoping to finish...

read more
Expanding our Fibre Network in Clayton, ON: Week Three Update

Expanding our Fibre Network in Clayton, ON: Week Three Update

  We’re already halfway through July, and the Fibre expansion project in Clayton is coming along nicely. Week two was a success, and now it’s onto week three. Week one started on Ramsay Concession 3C, where we began trenching to place the conduit into the ground, with a total distance of 1174 m. Last week, the conduit on Ramsay Concession 3C was completed, and we’ve started to install the...

read more

CONTACT US
Head Office

1760 Courtwood Crescent
Ottawa, ON K2C 2B5

TOLL-FREE: 1-866-257-8676

Rediscover Customer Service.

 

HOURS OF OPERATIONS

Support Hours:
Monday-Friday 8am-9pm
Saturday-Sunday 9am-5pm

Sales Hours:
Monday-Friday 8am-4pm

Billing Hours:
Monday-Friday 9am-5pm

TERMS OF SERVICE   |   PRIVACY POLICY  |  CORPORATE RESPONSIBILITY POLICYACCESSIBILITY  VOIP 911 TERMS

© Copyright 2021 Storm Internet Services |  All Rights Reserved.